Guide · 40 CFR 112

The 5-year SPCC plan review: what the signed statement must say (112.5(b))

Published October 2026 · PlanKeep

Short answer: at least once every five years, the owner or operator must complete a review and evaluation of the SPCC plan, and document it. For qualified facilities, the documentation is a signed statement that the review was completed, entered in a five-year review log. The review itself doesn't require re-certification by a Professional Engineer; but if the review shows the plan needs improvement, the resulting amendment runs on 112.5(a)'s six-month clocks.

What the rule requires

40 CFR 112.5(b) has three moving parts:

  1. Review at least once every five years. The clock runs from the plan's certification date, or from the last review, if one was completed in between.
  2. Evaluation, not a skim. As a result of the review, the plan must be amended within six months to include more effective prevention and control measures where applicable: the same amendment machinery as 112.5(a), followed by implementation within six months of preparation.
  3. A signed statement. Completion of the review and evaluation is documented in a log, with the reviewer's name and signature. EPA's own template gives the statement's working shape: "I have completed a review and evaluation of the SPCC Plan for this facility, and will/will not amend this Plan as a result."

For self-certified qualified facilities, the statement is the owner's or operator's. For PE-certified plans, EPA's guidance confirms the five-year review does not require the PE to re-certify, unless the facility has materially changed or the review itself requires an amendment, in which case the amendment follows its own certification path.

What the review actually evaluates

A review that means anything checks the plan against the facility as it exists now, not as it existed when certified:

  • The container list. Does every container in the plan still exist? Is every container on the ground in the plan? Have aggregate capacity or the largest single container crossed a qualification threshold (5,000 / 10,000 gallons) that changes your certification path?
  • Containment condition. Have dikes, liners, and drainage systems aged in ways the plan's descriptions no longer match?
  • The industry standard. Inspection standards get revised; the plan's inspection program should still name a current standard and a schedule you actually follow.
  • The spill history. Any discharges since the last review, even small ones, need to be reflected in what the plan says about response and prevention.
  • Personnel. Is the designated person accountable for discharge prevention still designated, still employed?
  • The amendment trail. Do the technical amendment log and the plan's body tell the same story?

The log entry

The five-year review log row is short, and it is evidence: review date, whether the plan will or will not be amended as a result, and the name and signature of the person authorized to review. Alongside it sits the technical amendment log covering everything since the last certification. Both live with the plan, which is the same binder (or system) an inspector asks for first.

A "will not amend" row is a legitimate outcome; plenty of five-year reviews find a facility unchanged and the plan sound. What's not legitimate is the row that never gets written.

Why facilities miss it

Five years is longer than most tenure cycles. The person who certified the plan has changed jobs; the plan is a PDF on a retired laptop; nothing reminds anyone. An inspector asks for the five-year review statement and the answer is a shrug: a documentation violation that costs nothing to prevent and is entirely self-inflicted.

PlanKeep tracks the review date from the plan's own metadata, opens the task when the window arrives, generates the signed statement in the expected form, and files it into the audit package next to the amendment log and inspection records. The answer to "when was your last five-year review?" becomes one click, not an archaeology project.

FAQ

When exactly is my five-year review due? Five years from the plan's certification date. If a review was completed in year five, the next clock runs from that review. PlanKeep computes it from the plan metadata so nobody has to reconstruct it.

Does the five-year review require a PE? Not by itself. PE re-certification is not a condition of the review under EPA guidance, but an amendment that results from the review follows 112.5(a)'s certification path, and PE-certified plans follow the PE path for their amendments.

What's the difference between the five-year review and an amendment? The review is the scheduled evaluation (112.5(b)); the amendment is the change mechanism (112.5(a)), triggered by facility changes or by the review's findings. The review can conclude with no amendment; a facility change forces an amendment regardless of the review calendar.

What does the statement need to say? That the review and evaluation were completed, and whether the plan will be amended as a result, signed and dated by the reviewer. EPA's Tier I template contains the exact form; PlanKeep's five-year review generator produces the same statement, already filed in the audit package.

Informational assessment only. Not legal advice, not PE certification.

Check your facility in 3 minutes

Free wizard: thresholds, Tier I/II verdict, and the reasoning behind it.

Open the wizard
The 5-year SPCC plan review: what the signed statement must say (112.5(b)) | PlanKeep